How you can have your first phone produced in China

 How you can have your first phone produced in China?

 How you can have business dealings with Chinese cellular phone producer?

The whole of the smartphone producing course of action

Mostly, cellphone integrators refers to the initial mobile handset makers who blueprint the mobile handset at the start, and next design the style and inner arrangement, following that, they open mould and debug the mobile’s software program simultaneously. When all things are all set, the mobile phone handset integrators will buy cell phone parts, for instance , mobile phone housing, LiPo battery, display screen panel, keyboard, and so forth., you will find roughly 100 components inside a cell phone.

mobile-phone-components

Subsequent to getting these mobile phone components,The entire handset manufacturing procedure shown as on the next paragraphs:

In short words:

outlined-Production-process

Details regarding Production Process Plan

detailed-production-process

Smartphone Production Schedule Plan

In theory, it will require 80-90 working days from defining a mobile phone product to mass production and shipping, provided that no NG takes place throughout the production process. The entire process comprises of 3 periods:

1st stage:

20-30 days to determine a mobile product, from ID to MD (Mechanical Design, also referred to as Structural Design) and get ready mould info.

2nd stage:

Thirty days from hardware design to sealed sample.

3rd stage:

Thirty days from small-scale production plan (PP) to mass production.

It will require as long as Sixty days from hardware design to sealed sample based on your business’s needs on smartphone level of quality and technology. In the event that you’ve placed an OEM order earlier, you’ll be able to reduce the delivery deadline days down to 30-45 days, as just a handful of actions of the production process have to be tailored, for example , touch panel and LCD sample during the structural design phase.

In many instances, Chinese OEM smartphone producers have their own production schedule plan for each and every component of OEM mobile phones. Once you place an OEM cell phone order, the producers will organize the producing in production line for producing and piecing together the Original equipment manufacturer cell phones. The overall production schedule plan consists of following parts: industry design (ID), mechanical design (MD), housing, liquid crystal display (LCD), touch panel (TP), PCBA and battery. Each item posesses a divided schedule plan period, for instance, ID/MD generally takes 30 days, however , the genuine time for ending ID/MD may perhaps need longer time- beyond Thirty days. Nevertheless, the items of whole production schedule plan can be overlapped in order to save time through the manufacturing process.

Item Details PlanTime(Day)
Adjusted(Day)
Actual(Day)
Remarks 
ID/MD From Brainstorming to Mould Produce 30 30+ 30+ All depend on actual day
Housing TO–T1  Modification Mould 7 7+ 7+ All depend on actual day
T1–T2  Modification Mould,can use
the sample for trial produce
4 4+ 4+ All depend on actual day
T2–Mass Produce (For Smartphone) 8 8+ 8+ All depend on actual day
LCD Mould–Sample 15 15+ 15+ All depend on actual day
Mass Produce or  reorder delivery time 15–18 / 18+ All depend on actual day
TP Mould–Sample 15 15+ 15+ All depend on actual day
Mass Produce or  reorder delivery time 15–18 / 18+ All depend on actual day
PCBA Prepare board and Paster 25 / / All depend on actual day
Mass Produce or  reorder delivery time 15–18 / 18+ All depend on actual day
Battery Lithium battery core 23 All depend on actual day
Mass Production 7 All depend on actual day
Li-polymer battery core 28+ All depend on actual day
Mass Producing 7 All depend on actual day